< Rückbau der Postpyramide abgeschlossen
06.11.2018 10:24 Age: 34 days
By: Sylvia Soggia

Deconstruction of Post Pyramid Completed


The Post Pyramide in 2006.

For the direct neighbours of the Überseering 30 construction site, there will be a bit more peace and quiet for the time being. The demolition of the post pyramid was completed on November 5th in 2018. This also marks the end of the noisy work.

Until the end of 2018, the Hagedorn company will at different times remove the recycling residues which are still on the site. At the same time, the district heating and cooling pipes will be laid on the site.

Preparatory work for the new building development will begin in mid-January 2019. The building of 523 residential units and an office complex will start around March 2019 with the excavation of the construction pit.

Further information about the construction site and the Ipanema new construction project is available here.